Re-development of ground-floor office space into a Community Diagnostics Centre, including X-ray machines and lung function testing facilities.
Challenging ceiling void coordination with very limited space.
Large fully HTM compliant Air-Handling Unit used in conjunction with a VRV air source heat pump heating and cooling system.
New high-efficiency LED lighting with automatic controls.
Addressable fire damper system as well as nurse call, panic buttons and access control.
Consideration to the first-floor services/operation and requirements to maintain segregation.
Pressure stabilisation dampers for areas that need to maintain a consistent negative pressure differential.
Challenging above ground drainage design with a lack of existing connections to below ground. The floor void was used in conjunction with drainage pumps to enable a network of pipework to be distributed around the floor onto main drainage stacks. All controlled via a central control panel.
Comprehensive Building Management System with energy metering integration.